A purely proactive scheduling procedure for the resource-constrained project scheduling problem with stochastic activity durations. Journal of Scheduling, 19 (4): 409-428, 2016.
Selected
The purpose of this research is to develop a new procedure for generating a proactive baseline schedule for the resource-constrained project scheduling problem. The main advantage of this new procedure is that it is completely independent of the reactive policy applied. This contrasts with the traditional methods that assume a predefined reactive policy. First, we define a new robustness measure, then we introduce a branch-and-cut method for solving a sample average approximation of our original problem. In a computational experiment, we show that our procedure outperforms two other published methods, assuming different robustness measures.
There is no pdf available for this paper. You might like to try to obtain the original source (see the doi, for example)
The doi for this publication is 10.1007/s10951-015-0423-3 You can link directly to the original paper, via the doi, from here
What is a doi?: A doi (Document Object Identifier) is a unique identifier for sicientific papers (and occasionally other material). This provides direct access to the location where the original article is published using the URL http://dx.doi/org/xxxx (replacing xxx with the doi). See http://dx.doi.org/ for more information
This pubication does not have a URL associated with it.
The URL is only provided if there is additional information that might be useful. For example, where the entry is a book chapter, the URL might link to the book itself.
@ARTICLE{2016-409-428-SI, author = {Lamas, Patricio and Demeulemeester, Erik},
title = {{A purely proactive scheduling procedure for the resource-constrained project scheduling problem with stochastic activity durations}},
journal = {Journal of Scheduling},
year = {2016},
volume = {{19}},
pages = {409--428},
number = {4},
note = {Selected},
abstract = {{The purpose of this research is to develop a new procedure for generating a proactive baseline schedule for the resource-constrained project scheduling problem. The main advantage of this new procedure is that it is completely independent of the reactive policy applied. This contrasts with the traditional methods that assume a predefined reactive policy. First, we define a new robustness measure, then we introduce a branch-and-cut method for solving a sample average approximation of our original problem. In a computational experiment, we show that our procedure outperforms two other published methods, assuming different robustness measures.}},